Paving of Stony Point Road is complete. No work is planned over Memorial Day Weekend including Monday, May 28th.

Expected activities following Memorial Day include: adjusting utility covers to the new grade and completing the traffic signal modifications. Striping will take place after those activities – expected to be during the weeks of June 4th and 11th.

Your continued patience is appreciated as we prepare to open the road in its new configuration, including two lanes of traffic in each direction and bike lanes.

If you have questions or concerns about construction activities, please call the project hotline at (707) 535-0799 or visit: www.stonypointroad.com